Helensburgh and Lomond bituminous surfacing scheme 2025/26

Programme status key
Description Status
SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) Scheduled
SCHEME UNDERWAY - WORK IN PROGRESS -  (Traffic Management as required, during works) In progress
WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) Complete

Last updated - 9th May 2025

Helensburgh and Lomond

Helensburgh and Lomond bituminous surfacing
Location Treatment type Duration - days Start month Status
A814 Main Road (A814) through Cardross Machine patch 14 July Scheduled
U242 Reay Avenue (Junction with A814) Cardross Inlay 5 July Scheduled
A814 Cardross Lyleston West Lodge Overlay 6 Sep Scheduled
U57 Charlotte street Bridge Helensburgh Inlay 5 July Scheduled
U002 Abercromby Crescent Helensburgh Inlay 14 Aug Scheduled
U299 Upper Glenfinlas street Helensburgh Machine patch 6 Aug Scheduled
U159 Jellicoe Place Helensburgh Inlay 6 Aug Scheduled
U144 Hardy Hill (no.65 to JCT Winston Rd Helensburgh  Inlay 4 Aug Scheduled
U103 East Montrose Street Helensburgh Patching 6 Sep Scheduled
U97 East Abercromby st (Railway bridge) Helensburgh Inlay 5 Sep Scheduled
A818 Luss Road Blackhill Overlay 8 July Scheduled
C75 Rhu Road Higher Helensburgh Patching 4 Sep Scheduled
A814 Rhu Lagarie House Overlay 7 Oct Scheduled
U324 Woodlea Crescent Garelochead Inlay 5 Oct Scheduled
U262 Shore Road Shandon PH2 Overlay 16 Oct Scheduled
B838 Church road Arrochar Overlay 5 Oct Scheduled
B833 Shore Road Cove Kirklea Overlay 10 Oct Scheduled
B833 Shore Road Kilcreggan @ pedstrian crossing Inlay 7 Oct Scheduled
U270 St Modans Way Rosneath Inlay 8 Oct Scheduled
East Princes St ( Henry Bell St - Geo St) Inlay 14 May Complete
A817 Haul Road @ A814  HFS ( "Anti-Skid" surfacing) Surface treat 5 July Scheduled