º£½ÇÉçÇø

Bute and Cowal bituminous surfacing scheme 2025/26

Programme status key
Description Status
SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) Scheduled
SCHEME UNDERWAY - WORK IN PROGRESS -  (Traffic Management as required, during works) In progress
WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) Complete

Last updated - 9th May 2025

Cowal

Cowal bituminous surfacing
Location Treatement type Duration - days Start month Status
A815 - St Catherines 40mph Overlay 5 May Complete
C60 Cammesreinach Brae Inlay 5 May Complete
 A8003  Royal Brae - Tighnabruaich Inlay 5 Sept Scheduled
C57 Glenbranter - North Scheme Overlay 3 July Scheduled
U17 Cowal Place - McArthur St to Cowal Ave Inlay 5 Sept Scheduled
B8000 Multiple Sites   short overlays Inlay 5 Sept Scheduled
A815 Sandbank - Rankins Brae Inlay 5 Sept Scheduled
A815 Sandbank - Fir Brae to Lazaretto Ferry Road Inlay 5 June Complete
A885 º£½ÇÉçÇø St - Stadium to Bencorrum Brae Inlay 5 Sept Scheduled
C7 Kames Middle Road Inlay 2 Sept Scheduled
B866 Shore Road Colintraive Overlay 10 Aug Scheduled
B828 - A83 to B839 Overlay 2 Oct Scheduled
B839 - A815 to Drimsyniebeag Bridge Overlay 2 Oct Scheduled
C9 Larach - Blairmore to Whistlefield Overlay 2 Aug Scheduled
U22 West Glendaruel (Camquhart  /  Bridge>A886) Overlay 10 July Scheduled
A8003 View Point South  -  Completion of widening Widening 40 June In progress
PSD  - U27 Millhouse / U17 Couston PH 1 - Future Years Patching 3 June Complete
B839 / B828 Passing Places  - Improvements & additional Construction 10 Oct Scheduled

Bute

Bute bituminous surfacing
Location Treatment type Duration - days Start month Status
A844 Kerrycroy  Overlay 4 June Scheduled
C3 Lubas Farm Patching 4 June Scheduled
U32 Foley Road Inlay 2 June Scheduled
U45 Longhill Terrace Inlay 3 June Scheduled
U41 King St, U50 Mill St & U62 Stuart St Inlay 2 June Scheduled
U64 Union St - North Leg Inlay 2 June Scheduled
C4 Roslin Road  - Minister's Brae to Rothesay Golf Club  Overlay/Inlay 2 July Scheduled